EN
Corporate

Owner was liable for insufficient project material and payment for extra work

logo
Legal news
calendar 11 May 2014
globus Denmark

A contractor had provided a quotation for insulation and exterior plaster work, however the owner had omitted to inform him that the conditions of the quotation were not in accordance with the actual conditions. The Court of Arbitration found that the contractor was entitled to payment for extra work and that the owner should have informed the contractor about the actual conditions.

An owner made an agreement with a contractor regarding insulation and exterior plaster work. When the works started the contractor found out that the insulation had to be done in more than one depth and this was not part of the contractor’s original quote. Moreover, the scope of work was much more extensive than what the contractor had assumed when preparing the quotation. Furthermore, the real area which should be covered with exterior plaster was bigger than what the owner had stated initially. Therefore, the contractor claimed extra payment. The owner did not find that this could be considered as extra work and he refused to pay the contractor.

During the proceedings, the contractor explained that he had based his quote on the drawings sent by the owner’s advisor in connection with the tender. Not until after signing the contract did the contractor receive more detailed project material. In that connection, it was not brought to the contractor's attention that there were deviations in the drawings compared to the previous drawings.

On the contrary, the owner claimed that the project material did not deviate and that, therefore, the contractor could not claim extra payment. Furthermore, the owner claimed to have a separate counterclaim despite the expiry of the 5-year limitation period.

The Court of Arbitration: Owner liable for project material

The Court of Arbitration found that the contractor could claim payment for extra work. The Court emphasized that it was the owner’s responsibility to inform the contractor about the deviations from the conditions on which the contractor had based his quotation. It was not enough that the owner had sent further drawings and other documents without making the contractor aware that these contained deviations.

In relation to the owner’s claim, the Court of Arbitration was not convinced that there was a concrete risk of development damage. Therefore, the owner was not entitled to compensation.

IUNO’s opinion

The decision shows that it is the owner’s responsibility that the project material is correct. Depending on the circumstances, a contractor can claim payment for extra work caused by insufficient facts about the actual conditions for the work. In this case, the Court of Arbitration emphasized that the agreement between the contractor and the owner was based on the quotation from the contractor. For that reason, the owner was responsible for informing the contractor about the deviations and modifications to the drawings which the contractor had based his quotation on.

The scope of work must be clear in connection with the tendering process. In case of deviations, it is not sufficient that the owner sends new and specified drawings after the tender. The owner must actively inform the contractor about any changes to the facts on which the contractor’s quotation is based.

[Court of Arbitration, case no. C-12847]

An owner made an agreement with a contractor regarding insulation and exterior plaster work. When the works started the contractor found out that the insulation had to be done in more than one depth and this was not part of the contractor’s original quote. Moreover, the scope of work was much more extensive than what the contractor had assumed when preparing the quotation. Furthermore, the real area which should be covered with exterior plaster was bigger than what the owner had stated initially. Therefore, the contractor claimed extra payment. The owner did not find that this could be considered as extra work and he refused to pay the contractor.

During the proceedings, the contractor explained that he had based his quote on the drawings sent by the owner’s advisor in connection with the tender. Not until after signing the contract did the contractor receive more detailed project material. In that connection, it was not brought to the contractor's attention that there were deviations in the drawings compared to the previous drawings.

On the contrary, the owner claimed that the project material did not deviate and that, therefore, the contractor could not claim extra payment. Furthermore, the owner claimed to have a separate counterclaim despite the expiry of the 5-year limitation period.

The Court of Arbitration: Owner liable for project material

The Court of Arbitration found that the contractor could claim payment for extra work. The Court emphasized that it was the owner’s responsibility to inform the contractor about the deviations from the conditions on which the contractor had based his quotation. It was not enough that the owner had sent further drawings and other documents without making the contractor aware that these contained deviations.

In relation to the owner’s claim, the Court of Arbitration was not convinced that there was a concrete risk of development damage. Therefore, the owner was not entitled to compensation.

IUNO’s opinion

The decision shows that it is the owner’s responsibility that the project material is correct. Depending on the circumstances, a contractor can claim payment for extra work caused by insufficient facts about the actual conditions for the work. In this case, the Court of Arbitration emphasized that the agreement between the contractor and the owner was based on the quotation from the contractor. For that reason, the owner was responsible for informing the contractor about the deviations and modifications to the drawings which the contractor had based his quotation on.

The scope of work must be clear in connection with the tendering process. In case of deviations, it is not sufficient that the owner sends new and specified drawings after the tender. The owner must actively inform the contractor about any changes to the facts on which the contractor’s quotation is based.

[Court of Arbitration, case no. C-12847]

Receive our newsletter

Aage

Krogh

Partner

Similar

logo
Corporate

26 March 2025

What you need to know about competitions on SoMe

logo
Corporate

13 March 2025

The Danish High Court reduced fine for covert marketing

logo
Corporate

3 March 2025

Get your campaign approved by the Danish Consumer Ombudsman

logo
Corporate

17 February 2025

Specific environmental statements can still be misleading

logo
Corporate

30 January 2025

Eco-friendly? Prove it!

logo
Corporate

24 January 2025

Environmental claims under scrutiny: The latest recommendations

The team

Aage

Krogh

Partner

Aurora

Maria Thunes Truyen

Associate

Emilie

Ulrich Krogh

Junior legal assistant

Frida

Assarson

Associate

Josephine

Gerner Amaloo

Legal assistant

Karoline

Skak Kristensen

Legal assistant

Maria

Kjærsgaard Juhl

Associate

Matilde

Grønlund Jakobsen

Senior Associate